Permits and compliance

Permits, and what actually goes wrong.

The paperwork is not the hard part. Finding out at the wrong moment that it was never done is the hard part.

Permit and compliance documentation for a villa build in Bali.

A villa in Bali needs a PBG, the building approval, before work starts, and an SLF, the certificate that the finished building is fit to occupy, after it is done. The SLF process runs from a final inspection carried out between 90 and 100 percent of the build, and the certificate typically follows three to six months later, sometimes up to nine.

The most common mistake we see is not getting them at all. It works, right up until it does not: a fire, an injury on the property, a neighbour who complains, or an official who drives past a building that is visibly where it should not be. Then it is not a paperwork problem any more.

The timings, as they really are

Numbers from our own jobs rather than from a government service standard.

Final inspection
At 90 to 100 percent of the build
SLF, typical
Three to six months after inspection
SLF, slow but normal
Up to nine months
Twelve months or more
Something is wrong with the plans or the consultant

Why it takes as long as it does

The department handling these is badly understaffed relative to the number of applications going in, and that is the single biggest driver of the timeline. It is not a queue you can talk your way to the front of, and anyone promising you a fast certificate is describing a relationship rather than a process.

What you can control is whether your application is a clean one. A set of plans that matches what was actually built, submitted by a consultant who does this constantly, moves through. One that does not comes back, and each return costs weeks rather than days.

What SLF is actually checking

It works much like a building code inspection anywhere else. It looks at setbacks, at how the building sits on the plot, at the shape and pitch of the roof, and at height.

Some of these you can breach and still be issued the certificate on payment of a fine, and that is a normal and openly acknowledged part of the process. Others you cannot, and height is the one to be careful about. A building that is over the limit for its zone is not a fine, it is a problem, and it is a problem that exists in concrete rather than on paper.

The old rule that nothing may be built taller than a coconut tree is a real piece of history rather than a myth, and it is not what governs now. Every zone carries its own limit in metres. We check the figure for your specific plot rather than quote you an island-wide number, because the island-wide number does not exist.

Where owners actually come unstuck

Four failure modes, in the order we meet them.

  • Not applying at all, on the reasoning that plenty of people do not. It holds until the day something happens on the property, and then the absence of a certificate turns an incident into a liability.
  • Building something that does not match the drawings that were approved. The inspection compares the two, and reconciling them afterwards is far more expensive than drawing it correctly once.
  • Leaving the application to the end. The inspection happens near completion, so a build that ignored permits until handover has not saved time, it has moved the entire delay to the point where the owner wanted to move in.
  • Using a consultant who does this occasionally. If your certificate is taking a year, this is usually why.

How we handle it

Permits are inside the contract rather than a service you are referred out for. The same team that draws the villa submits it, which removes the most common cause of a rejected application, and the build programme is planned around the inspection rather than surprised by it.

We would also rather lose a job than take one where the zoning does not support what the client wants to build. That conversation happens at the survey stage, before land is committed to, because a plot that cannot carry the villa in the client's head is not a problem that gets better once it is bought.

Questions we get asked about permits

What is the difference between PBG and SLF?
PBG is the approval to construct the building, and it comes before work starts. SLF certifies that the finished building is fit to be occupied, and it comes after, following an inspection carried out between 90 and 100 percent of completion. You need both, and they are not interchangeable.
How long does SLF take in Bali?
Typically three to six months from the final inspection, and sometimes up to nine. If it is running past twelve months, in our experience the problem is the plans or the consultant rather than the department.
Can I build without a permit and sort it out later?
People do, and it often holds for a year or two. What it means is that you are carrying an uninsured risk on a building you cannot easily sell, and the moment there is a fire, an injury, a complaint from a neighbour or an official driving past, it stops being deferred and becomes urgent. We will not build that way.
How high can I build?
It depends on the zone, and every zone carries its own limit in metres. We would rather check the figure for your plot than print an island-wide number that would be wrong somewhere. Height is also one of the breaches that cannot be settled with a fine, so it is worth establishing before the design is finished rather than after.
Can setbacks and roof shape be negotiated?
Some minor breaches can be resolved with a fine and the certificate still issues, which is a normal part of how the system works. That is not the same as designing to breach on purpose, and it is not true of everything. We will tell you which category a particular decision falls into before you commit to it.